Quick Details
- Processing Time:-
- Port:-
- Supply Ability: -
- Brand Name:-
Product Description
BAISC INFORMATION
A. Product Name
High Reflective Thermoplastic Road Marking Paint
B. Use For
Concrete and asphalt floor
C. Components
C5 Petropols, EVA, PE wax, titanium dioxide, filler materials…
D. Appearance
Powder
E. Standard
JT/T280-2004
F. Color
White and yellow (OEM)
G. Weight
25kg/bag
H. Density
2.01/ cm³
I. Film Thickness
1.8-2.0mm
PHYSICAL CHARACTERISTICS
A. Compression Strength
23.8MPa
B. Fluidity
38
C. Abrasion Resistance
56.8
D. Glass Beads
22.9%
E. Softening Temperature
104°C
F. Heating Temperature
180-200°C
G. Drying Time After Marking
Touch dry—3 mins
Full dry—10 mins
H. Shelf Life
Up to 24 months
I. Storage
Store in a tightly sealed container in a cool & dry place
J. Area Of Line
1 Ton thermoplastic paint can mark about 225 m2
FEATURES
A. High usage ratio
B. Save the cost of gas
C. Excellent durability
D. Strong adhesion power
E. High dirty pick-up resistance
F. Bright-color and not faded easily marking line
RECOMMENDATION
A. Equipment
Pre-heater
Thermoplastic road marking machine
Primer sprayer
Road blower
Road sprayer
B. Dosage Ratio
Thermoplastic paint: 1Ton
Primer: 32KG
Glass beads: 100KG
PROCESS
A. Clean
Clean intended application area thorough
B. Layout
Outline the area where the marking will be placed using titanium dioxide
C. Apply primer
Apply the appropriate amount of primer needed for the surface
D. Melt
Heat paint to be melted using pre-heater
E. Position A
Pour melted paint into big container of road marking machine
Position B
Pour glass beads into small container of road marking machine
F. Mark
Mark thermoplastic line using road marking machine
G. Cool
Thermoplastic line will cool within a period of time
ATTENTION
A. Ensure road surface is stable, dry and clean
B. It is better to apply above 0°C
C. Heating paint in the pre-heater should be between 180-200 °C
D. Lift the heating temperature properly when working in a low temperature environment
E. Mixing the melted paint evenly and keeping it warm for 3-5 mins before marking the road
F. Allow primer to dry before applying paint
G. Primer is applied a few wider than the width of the thermoplastic line
H. New asphalt and concrete must be allowed to cure for a minimum of 30 days before applying paint